Master Timeline

Countdown-based operational timeline. Derived from the Pop-Up Playbook and meeting notes.


6-12 Months Out (Now - Feb 2026)

  • Lock down facilities (Commons Hub confirmed as primary venue)
  • Determine room types: dorm, double, single/deluxe (Herrnhof)
  • Draft website and deploy to Vercel
  • Public announcement with QR code at CCC
  • DNS: Point valleyofthecommons.com to votc26.vercel.app
  • Finalize ticket pricing and accommodation pricing
  • Confirm association legal structure (VoTC Association, registered in Vienna)
  • Start reaching out to potential sponsors
  • Lock in initial key community partners

4-5 Months Out (March - April 2026)

  • Open applications (allow deposits to secure spots)
  • Finalize application form
  • Formal announcement with finalized dates, pricing, and amenities
  • Start content structure drafting
  • Invite key speakers
  • Start meeting with local businesses and orgs for partnerships
  • Start inviting/sponsoring residents
  • Begin sponsor outreach with pitch deck
  • Design "acceptance flow"

2-3 Months Out (May - June 2026)

  • Finalize acceptance flow
  • Start accepting applications and reviewing
  • Begin building virtual community
  • Weekly check-in meetings with track leads
  • 1 June: Early-bird pricing ends (10% increase)
  • Book catering / local food partnerships
  • Confirm A/V setup for talks and workshops
  • 22-28 June: CoFi Week

1 Month Out (July 2026)

  • Online pre-engagement begins
  • Self-organization online begins
  • Finalize full schedule with all speakers and session times
  • Confirm all community partner programming slots
  • Print materials: schedules, signage, maps, emergency info
  • Final room allocations confirmed
  • Tech setup: Wi-Fi tested, projectors, sound, streaming

Event Month (August - September 2026)

DateEvent
16-22 AugCCG (Crypto Commons Gathering) - pre-event
23 AugFinal prep day, early arrivals
24 AugVoTC Day 1 - Check-in, orientation, opening
24-30 AugWeek 1: Return of the Commons
31 Aug - 6 SepWeek 2: Cosmo-local Production and OVA
7-13 SepWeek 3: Future Living
14-20 SepWeek 4: Governance and Funding
20 SepClosing ceremony, checkout begins
21 SepFull checkout, debrief

Post-Event

  • Debrief meeting with full team
  • Financial reconciliation
  • Participant feedback survey
  • Public write-up / report
  • Feed learnings back into long-term Valley of the Commons permanent village plan